Question No : 1
DRAG DROP
You are a project manager in an organization that is using Microsoft PPM for work management.
You have already accepted all status updates in the Approval Center, but you are still unable to see the updates in your project schedule.
You need to ensure that status updates are reflected in your project schedule.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.



正解:

Question No : 2
You are a project manager for an organization that is using Microsoft Project.
You have enabled Single Entry Mode and team members update their task using timesheets.
You need to see how these updates impact your project before you approve the tasks.
What should you do?

正解:

Question No : 3
DRAG DROP
You are an administrator for your company’s Microsoft PPM environment. You implement several project level enterprise custom fields and add these fields to new and existing views.
Some users report they spend too much time scrolling left and right in a view named Team Status. You determine that the column width for the Enterprise Project Type field may be causing the issue.
You need to reduce the amount of scrolling.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.



正解:

Question No : 4
DRAG DROP
You are the administrator for an organization that uses Microsoft PPM.
Users must be able to create projects by using predefined templates.
You need to create a new Enterprise Project Template and make it available for users.
In which order should you perform the actions? To answer, move all of the actions from the list of actions to the answer area and arrange them in the correct order.



正解:

Question No : 5
The SharePoint Farm administrator for a company installs Microsoft PPM and grants you administrative rights for PWA. The PWA instance is accessible at the URL: https://AppServer/Live.
You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.
You need to ensure that the RBS is implemented.
What should you do first?
A. Run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
B. Ask the SharePoint administrator to run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
C. From Settings, select Manage Groups.
D. From Site Settings, activate the Project Web App Connectivity feature.

正解: B

Question No : 6
DRAG DROP
You are the Microsoft PPM administrator for a large organization.
You need to ensure that line managers can delegate timesheet approvals to their team members.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.



正解:


Explanation:
References: https://technet.microsoft.com/en-us/library/cc197631.aspx

Question No : 7
You are managing an e-commerce portal development project by using Microsoft PPM.
In order to communicate the status of your project to your stakeholders, you want to create a real time project status report using Microsoft Excel in Office Online Services.
You need to show information about your overall project status and late tasks on your status report.
What should you do?
A. From the Report tab in Project Pro for Office 365, select the In Progress | Late Tasks report. Save the report as a .pdf file to the designated reports library in PWA.
B. From the Project Details view in PWA, change the filter to the Late Tasks filter and copy and paste the tasks into Excel. Save to the designated reports library in PWA.
C. From the English folder in the PWA Data Connections library, open the OData Task Data .odc data connection file.
D. From the Power Query tab in Excel, select the From other sources | From ODBC option to add data to the report.

正解: C

Question No : 8
HOTSPOT
Your organization uses Microsoft PPM and Power BI to manage projects. You create status reports for projects by using Microsoft Excel files and Power BI Desktop. You plan to combine several specific reports into a single Power BI dashboard.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.



正解:

Question No : 9
DRAG DROP
You are project manager in your company’s PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.



正解:

Question No : 10
You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI.
You need to import into Power BI by using the Microsoft Project Online content pack.
What should you do?

正解:
Explanation:
References: https://powerbi.microsoft.com/en-us/documentation/powerbi-content-pack-project-online/

Question No : 11
Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
Which three configuration changes should you make? Each correct answer presents part of the solution.

正解:

Question No : 12
Your organization is using Microsoft PPM to manage and track all projects.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organization’s strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.

正解:
Explanation:
References: https://technet.microsoft.com/en-us/library/dn641991.aspx

Question No : 13
HOTSPOT
You are evaluating the requirements for creating a new portfolio analysis.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.



正解:


Explanation:
References: https://technet.microsoft.com/en-us/library/dn641991.aspx

Question No : 14
You are a project manager using Microsoft PPM.
You need to create a new project that uses one of your company’s templates.
What are two ways to achieve the goal? Each correct answer presents a complete solution.

正解:

Question No : 15
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.

正解: