Question No : 1
You are a project manager who uses Project Professional 2013.You work on a construction project that requires propane as a fuel source for your equipment.The foreman requires that you enter project costs associated with all work completed on your project.The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane.Each time the tank is refilled, you must pay a fee of $20.You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.
What should you do?

正解:

Question No : 2
You manage a project for an organization that relies heavily on schedule baselines in Project Standard 2013.A change is approved for an in-progress project which you manage.You enter the new tasks necessary to include the changes to the project schedule.You need to update the baseline in the most efficient manner.
What should you do?

正解:

Question No : 3
You are a project manager who uses Project Professional 2013.You work in a software development project, which is in progress and has reached 60% of actual progress.Your company decides to use the new Project Reports views to communicate all the project progress across the key users.They also decide to report information about a specific period only, normally one month behind the current day.You need to access the report view that your company previously created; however, you must only modify the period displayed in the report and ensure that another period will not be presented.What should you do?

正解:

Question No : 4
You are project manager who uses Project Professional 2013.Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project.The task list contains over 100 items.You need to create a project based on the tasks in the SharePoint list in the most efficient manner.
What should you do?

正解:

Question No : 5
You are a senior project manager, and your organization uses Project Standard 2013.You are managing a large ERP project with both part-time and full-time resources.The part-time resources have strict contractual limitations regarding working days and hourly availability.You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.What should you do?

正解:

Question No : 6
Your organization uses Project Professional 2013 and Microsoft SharePoint 2013.You are responsible for a project with resources in different offices.All offices share the same SharePoint intranet, and all resources have valid accounts to log into the company intranet.Your project plan already has the correct names and assignments for each resource involved in this project.You need to share and receive project plan updates dynamically with your resources.
What should you do?

正解:

Question No : 7
You are a project manager who uses Project Professional 2013.You have created a project which involves three other colleagues who are also using Project Professional 2013.You and your colleagues are over budget and cannot spend any more money on this project.
To ensure that the latest version of the project file is always the one being used, you need to save, share, and sync this project plan file among your colleagues without using email.
What should you do?

正解:

Question No : 8
You are a project manager who uses Project Standard 2013.Your current project has resources with the standard calendar as the base calendar.Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks.When you assign a resource to one of these tasks, you get an error.You need to correctly assign the resource.What should you do?

正解:

Question No : 9
You work as a project manager for a construction company that uses Project Professional 2013.You have created your work breakdown structure (WBS) and are adding resources to your tasks.However, one of your tasks requires multiple resources.You have the name of the project’s lead support individual, and you have been provided with the equivalent of three full-time support resources.These three resources are not named individuals but are part of a group.The actual individuals from this group will change based on coverage schedules.The resources have the following cost structures:
・The lead is billed out at $175/hour.
・The group resources are billed out at $140/hour.You need to add these resources to the schedule and track your project costs.Which two actions should you perform? (Each correct answer presents part of the solution.Choose two.)

正解:

Question No : 10
Your company uses Project Professional 2013.You are building a schedule by using predecessors to help determine a logical duration.The following image shows a baselined list of tasks with predecessors:
You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule.You need to determine what the results are to the schedule when inactivating Task C.How should you answer?

正解:

Question No : 11
You manage a project by using Project Standard 2013.
You need to use the Baseline2 fields to calculate Variance at Completion (VAC).You have already set Baseline2.What should you do?

正解:

Question No : 12
You are managing a project by using Project Professional 2013.
Your project schedule contains 1000 tasks which are in outline format.You discover that the Design summary task is located below the Build summary group of tasks.You need to move the Design summary task and its detail tasks to the proper location.
What should you do?

正解:

Question No : 13
You are a project manager who uses Project Professional 2013.You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode.What should you do?

正解:

Question No : 14
You are a program manager for a complex software development project.You use Project Professional 2013 to manage your project.Your resources work on many different projects across the program, and you need to resolve resource overallocations.Your project team uses a resource pool to manage resources.Resource1 has been assigned to assist on a project that is on the critical path.After assigning Resource2 to the task, you notice that Resource1 is overallocated during the month of November.Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to.
Using resource leveling in Project Professional 2013, you need to resolve the overallocation for Resource1 for the month of November only.
What should you do?

正解:

Question No : 15
You use Project Professional 2013 to manage a project schedule which includes all task relationships.The resource who is assigned to the “Develop software delivery” task is no longer available to work on your project.You can find another resource to perform this task, but you are not sure when the resource will become available.
You need to know which future tasks could be affected as a result of the resource leaving your project.What should you do?

正解: