Question No : 1
A BPM analyst needs to make a change to the connections in the following process diagram.
The order of activities needs to be changed so that "Grind Beans" is followed by "Brew Coffee". "Heat Milk" will come last after "Brew Coffee".



How should the BPM analyst make this change to the connection?

正解:

Question No : 2
A BPM analyst is working with a facilities manager to map out a process that lists the responsibilities of the facilities manager.
In the event of a damage to a building, the facilities manager must take the following actions.
- If the damage is caused by fire, the facilities manager must immediately call the fire service.
- If there is anyone injured, the facilities manager must immediately call the nearby hospital ambulance service.
- If the damage is greater than $5000, the facilities manager must notify the insurance agent immediately.
- The facilities manager must always submit a damage report to the building manager within 1 week of the incident.
How should the BPM analyst model this process?





正解:

Question No : 3
The project manager needs assistance from the BPM analyst to determine the initial level of effort for processes in a process inventory.
For each process, the BPM analyst should provide a list of process details that include:

正解:

Question No : 4
During discovery, a process owner presents the BPM analyst with over 350 Key Performance Indicators (KPIs) determined by executive management based on the goals of the company.
What action should the BPM analyst recommend to the process owner?

正解:

Question No : 5
A company needs the BPM analyst to provide a business value and impact assessment to only proceed with processes that align with their corporate strategy. The company's corporate strategy is to begin with small quick win pilots that require low effort and low impact and then scale to large programs that are low effort and high impact.



In the exhibit below, which quadrants contain the processes the BPM analyst should recommend?

正解:

Question No : 6
Calculate user story points

正解: A

Question No : 7
Performance Evaluation.
The Human Resource (HR) Department has a limited budget and is pressured from head office to provide value to the business as soon as possible.



The BPM analyst worked with the HR team and completed the effort impact matrix for these 4 processes in order to identify a suitable process candidate Based on the Exhibit, which process should the BPM analyst recommend?

正解:

Question No : 8
Does this project have enough IT challenges?

正解: B

Question No : 9
The project manager needs assistance from the BPM analyst in building a process roadmap.
What tool should the BPM analyst use to create a detailed list of areas of opportunity?

正解:

Question No : 10
A BPM analyst is performing a process inventory analysis at a company that has many processes and has gathered all required information to calculate a priority value for each process in order to rank them.
How should the BPM analyst compute this?

正解:

Question No : 11
A BPM analyst is documenting process problems during a discovery session.
As a problem is raised, what are the two key factors the BPM analyst needs to capture about each problem to be able to prioritize them later?

正解:

Question No : 12
A company that processes applications has been using IBM Business Process Manager V8.0 over the last year. The company has asked IBM to analyze its processes in production because it wants to continue improving its processes. The IBM BPM team sends a BPM analyst.
What should the BPM analyst do?

正解:

Question No : 13
A company needs to improve their hiring process and hired a BPM analyst to analyze their current process. The analyst completed documenting the current state process of submitting the hiring request (refer to the process diagram below) and did a "Value-Add" analysis with the process stakeholders.



Identify the "Business Value Add" activities in this process.

正解:

Question No : 14
A BPM analyst is helping to identify and select the appropriate solution for process improvement in a large BPM project.
What are the business levers the BPM analyst should focus on?

正解:

Question No : 15
A BPM analyst is modeling the process for acquiring membership at a club. The BPM analyst interviewed the front office supervisor, who provided the following description of the first activity "Enter Application": "One of our receptionists receives a paper application from a potential client, an applicant. The receptionist first looks up the client's name and address to see if it exists in our system, then enters the information from the paper application into the system, and assigns a membership number to the application. When the application entry is complete, the receptionist sends it to the manager for an initial review. “The BPM analyst has created the discovery map and now needs to enter information from the above description into the Details fields in Blueworks Live for the activity "Enter Application".
For the activity "Enter Application", who is the Supplier?

正解: