Question No : 1
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?

正解:

Question No : 2
What is the flag used for WBS elements for which you want to plan costs?

正解:

Question No : 3
Which transaction along with suitable selection criteria allows you to specify which networks and sub networks are to be taken into account as part of overall network scheduling?

正解:

Question No : 4
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned? There are 3 correct answers to this question.

正解:

Question No : 5
In progress tracking what are the different ways of assigning the dates of events that are assigned to network components while evaluation? There are 3 correct answers to this question.

正解:

Question No : 6
Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined?

正解:

Question No : 7
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.
How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?

正解:

Question No : 8
Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?

正解:

Question No : 9
In requirements grouping which indicator must be set for WBS elements that determines whether the requirements may be grouped into one WBS element and how?

正解:

Question No : 10
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?

正解:

Question No : 11
Which function allows you to check consistency of the dates within the project structure with or without taking activities into account?

正解:

Question No : 12
Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?

正解:

Question No : 13
How do you optimize cash flows to maximize project profits and reduce project costs?

正解:

Question No : 14
Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.
In this scenario planned costs are determined for which of the following? There are 3 correct answers to this question.

正解:

Question No : 15
Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?

正解: