Question No : 1
A new Product Owner has joined an existing Scrum Team that has been working together for eight Sprints. The Development Team has grown to have a good understanding of the functionality and business for the product they have been building. The Product Owner, being new to the company, is unsure about his responsibilities.
As a Scrum Master explain what two acceptable ways of helping the Product Owner would be. (Choose two.)

正解:
Explanation:
The ones that are closest to the work are the best ones to understand and explain what the work is and what the needs of the users and product are.

Question No : 2
In what two ways is velocity and technical debt related? (Choose two.)

正解:
Explanation:
Technical debt is a natural occurrence when developing complex products. It is a concept in software development that reflects the implied cost of additional rework caused by choosing an easy solution now instead of using a better approach that would take longer. And how it is managed will depend on the team AND context of the situation.

Question No : 3
Steven is a Scrum Master on a new Scrum Team.
What would be the best way for him to determine if the Product Owner is interacting enough with the Development Team during a Sprint?

正解:
Explanation:
Outcomes of the Scrum Team are affected by the Product Owner’s participation and availability. During a Sprint he/she is responsible for answering questions from the Development Team about items in the current Sprint and optimizing the value of the work the Development Team does.

Question No : 4
At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint.
Which of the following two actions would you support? (Choose two.)

正解:
Explanation:
All events are time-boxed events, such that every event has a maximum duration. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal.

Question No : 5
During the Sprint Review, the Product Owner decides to release the current Increment to production. The stakeholders suggest temporarily delaying the next Sprint in order to respond more quickly to user feedback after the release. The Product Owner prefers to continue to the next Sprint and make progress towards the next release. Steven, the Scrum Master, begins facilitating the discussion.
What would be two acceptable outcomes of the discussion? (Choose two.)

正解:
Explanation:
A new Sprint starts immediately after the conclusion of the previous Sprint. Delaying the start of the next Sprint interrupts progress and can reduce the Time-to-Market. Shortening the Sprint length allows the team to respond quicker to changes outside of the Sprint plan and while still allowing delivery of business value. Adding user feedback to the Product Backlog helps the Product Owner with ordering the backlog to maximize the flow of value.
During the Sprint no changes are made that would endanger the Sprint Goal.

Question No : 6
After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The Product Owner comes to the Scrum Master asking for advice.
What is the best action for a Scrum Master to take?

正解:
Explanation:
The highest priority of agility is to satisfy the customer through early and continuous delivery of valuable software. Because the Development Team is the one doing the work and increments must meet performance standards, they can expand their Definition of Done to include more stringent criteria for higher quality.

Question No : 7
Scrum addresses which of the following four risks in software development? (Choose four.)

正解:
Explanation:
Scrum is a framework within which people can address complex adaptive problems, while productively and creatively developing, delivering, and sustaining complex products of the highest possible value. Scrum employs an iterative, incremental approach to optimize predictability and control risk.

Question No : 8
Steven is a Scrum Master of a Scrum Team that is new to Scrum. At the halfway point of the Sprint, the Product Owner comes to Steven telling him that he is concerned the Development Team will not be able to complete the entire Sprint Backlog by the end of the Sprint.
What should Steven do in this situation?

正解:
Explanation:
Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes from experience and making decisions based on what is known. The Sprint Backlog is a forecast by the Development Team about what functionality will be in the next Increment and the work needed to deliver that functionality into a ‘Done’ Increment. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint. This emergence occurs as the Development Team works through the plan and learns more about the work needed to achieve the Sprint Goal.
Why C is incorrect:
a) The Dev Team does not commit to finishing all items in the Sprint Backlog. Committing to completing all items would be fixed scope and fixed time leaving no room to adapt. They commit to the Sprint Goal and doing the right thing.
b) It’s also incorrect for the PO to focus on completing the entire Sprint Backlog. Finishing everything should not be his main focus. Having a shippable increment that meets the Sprint Goal is more important than trying to finish everything. The advice in option C is equivalent to “Don’t worry, they’ll get everything done.” but because of the complex domain, you cannot guarantee everything will get done.

Question No : 9
Steven is a Scrum Master of a Development Team that has members working in different cities and time zones. Organizing the Scrum events is time consuming and requires a lot of effort to set up and run. The Development Team proposes to only hold the Daily Scrum on Mondays.
Which two responses would be most appropriate from Steven? (Choose two.)

正解:
Explanation:
The Scrum Master is responsible for ensuring that the Scrum Team understands the purpose and value of the Scrum events. Because the Daily Scrum is owned by the Development Team, it will decide how best to run the event. And if needed the Scrum Master will coach the team to ensure the decisions stay within the boundaries of the Scrum framework.

Question No : 10
Which two scenarios would best represent a self-organizing Development Team? (Choose two.)

正解:
Explanation:
A self-organized team is a team that is able to self-manage and decide how best to accomplish their work.

Question No : 11
At the fifth Sprint Retrospective, the Product Owner mentions that he is surprised about the amount of technical debt that has built up in the system and that the product is not able to support an adequate number of users. Peter, the Product Owner, is upset that the product will need several more Sprints to address the scalability issues in order to meet his expectations.
What factors may have led to this?

正解:
Explanation:
Each component within the Scrum framework serves a specific purpose and is essential to Scrum’s success and usage. Scrum’s roles, events, artifacts, and rules are immutable and although implementing only parts of Scrum is possible, the result is not Scrum.

Question No : 12
Steven is a Scrum Master for three different teams building a single product from the same Product Backlog. Development Team members from each team have approached Steven complaining that their teams need Nicole, an external specialist, to commit full time for their next Sprint.
Which three acceptable solutions would Steven consider? (Choose three.)

正解:
Explanation:
The Scrum Master is responsible for removing impediments within the current context of the situation AND boundaries defined by the Scrum framework.

Question No : 13
You have been hired as a Scrum Master for a company that has been doing business for over fifty years. In order to stay competitive, they have started an initiative to digitize their legacy systems. The company has several Scrum Teams working on different components that will be integrated to a single back office platform.
Your team is responsible for building the back office platform and integrating all other components. The Scrum Teams work in two week Sprints and are expected to deliver all functionality in six Sprints.
During development the requirement changes in the other components have been slowing down your team’s progress. Because of these changes, your team has estimated that they will not be able to deliver all expected work within the original timeframe. The Scrum Teams working on the other components confirm that they are still on track to meet the expected delivery date. The program manager in charge of the digitization initiative is upset and angry with your team.
As a Scrum Master, what could you do to help the Product Owner?

正解:
Explanation:
The Scrum Master serves the Product Owner in several ways, including:
- Finding techniques for effective Product Backlog management;
- Helping the Scrum Team understand the need for clear and concise Product Backlog items;
- Understanding product planning in an empirical environment;
- Ensuring the Product Owner knows how to arrange the Product Backlog to maximize value.

Question No : 14
By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team’s Definition of Done.
What two things should happen with the item? (Choose two.)

正解:
Explanation:
At the end of a Sprint, the new Increment must be ‘Done’, which means it must be in useable condition and meet the Scrum Team’s definition of ‘Done’. Scrum Team members must have a shared understanding of what it means for work to be complete, to ensure transparency. This is the Definition of Done for the Scrum Team and it is used to assess when work is complete on the product Increment.

Question No : 15
Individual Development Team members have been approaching Steven, the Scrum Master, to complain about Chris. Chris has the most experience on the system they are building. He often questions the choices team members make in design and architecture making them feel bad.
What are two good ways for Steven to address this problem? (Choose two.)

正解:
Explanation:
Conflicts are a natural occurrence and the Scrum Master coaches the Development Team on the value of resolving conflicts. Leaving conflicts unresolved can impact the Scrum values of openness and respect diminishing trust. Lower trust levels will impact the Scrum Team’s effectiveness and can cause impediments in the future. It is the responsibility of the Scrum Master to remove impediments that hinder the team through conflict resolution and facilitation.